Notice Text:
Nominated Volume Affected
|
August 13, 2026
To: All Transwestern Pipeline Customers
Subject: Bloomfield Compressor Station Maintenance- Located on the San Juan Lateral.
Gas Day September 8th thru September 11th, 2026 (4 days)
Bloomfield Capacity will be reduced from 1,610,000 MMBtu/d to 600,000 MMBtu/d. Harvest Valverde capacity will be reduced from 230,000 MMBtu/d to zero.
Gas Day September 12th, 2026 thru September 14th, 2026
Bloomfield Capacity will increase from 600,000 to its original capacity of 1,610,000 MMBtu/d. Harvest Valverde capacity will increase back up to the original capacity of 230,000 MMBtu/d. Gas Day September 15th thru September 18th, 2026 (4 days)
Bloomfield Capacity will be reduced from 1,610,000 MMBtu/d to 600,000 MMBtu/d. Harvest Valverde capacity will be reduced from 230,000 MMBtu/d to zero. Gas Day September 19th, 2026
Bloomfield Capacity will increase from 600,000 to its original capacity of 1,610,000 MMBtu/d. Harvest Valverde capacity will increase back up to the original capacity of 230,000 MMBtu/d. Based on current scheduled volumes through the Bloomfield Station (Blanco Hub), this maintenance may not impact any scheduled volumes during this timeframe.
Interconnects potentially affected:
POI 56423 - Harvest Valverde POI 500632 - Trans-Colorado POI 56419 - Harvest Milagro POI 500516 - Harvest Kutz POI 78424 - Conoco BlancoPlant POI 500535 - Harvest Ignacio POI 500536 - IKAV (BP) Florida POI 78121 - La Plata Red Cedar POI 500538 - Red Cedar Arkansas Loop POI 500533 &500534 - Northwest Ignacio POI 500631 - CEP La Plata
Transwestern reserves the right to revise the above listed schedule. Please continue to monitor Transwestern website for updates and schedule changes.
|