Updated as of
|
10/8/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
Listed below is a summary of the
planned outages that could affect capacity or impact any receipt/delivery
locations during the TGC 2020 outage season. This schedule is not a complete
list of all outages and is subject to change as the season progresses to
reflect any project delays, cancellations or additions. Additionally,
anticipated impact and restrictions are subject to change.
*All scheduled dates represent gas days as defined in the TGC Tariff to mean
a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m.
(Central Clock Time).
|
|
|
|
|
|
|
|
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated
Impact
|
Meter(s)
Impact
|
|
04/05/2021
|
04/16/2021
|
Pollock
|
5303
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
04/26/2021
|
05/07/2021
|
Pollock
|
5305
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
05/17/2021
|
05/28/2021
|
Pollock
|
5306
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
06/14/2021
|
06/25/2021
|
Pollock
|
5307
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
07/12/2021
|
07/23/2021
|
Pollock
|
5302
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
09/13/2021
|
09/24/2021
|
Pollock
|
5301
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
10/04/2021
|
10/15/2021
|
Pollock
|
5321
|
Minor AI
|
No Impact to Shippers Expected
|
None
|
|
04/20/2021
|
04/20/2021
|
Johnsonville
|
100-2
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
04/22/2021
|
04/22/2021
|
Johnsonville
|
100-2
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
03/16/2021
|
03/16/2021
|
Joppa
|
100-3
Line
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
03/19/2021
|
03/19/2021
|
Joppa
|
100-3
Line
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
09/20/2021
|
10/08/2021
|
Joppa
|
5801
|
Major A.I.
|
No Impact to Shippers Expected
|
None
|
|
03/15/2021
|
04/07/2021
|
Joppa
|
5802
|
Minor
A.I.
|
No
Impact to Shippers Expected
|
None
|
|
08/02/2021
|
08/27/2021
|
Joppa
|
5803
|
Minor
A.I.
|
No
Impact to Shippers Expected
|
None
|
|
04/19/2021
|
05/14/2021
|
Joppa
|
5805
|
Minor
A.I.
|
No
Impact to Shippers Expected
|
None
|
|
06/07/2021
|
07/09/2021
|
Joppa
|
5806
|
Minor
A.I.
|
No
Impact to Shippers Expected
|
None
|
|
10/18/2021
|
10/29/2021
|
Joppa
|
5807
|
Minor A.I.
|
No Impact to Shippers Expected
|
None
|
|
10/25/2021
|
10/28/2021
|
Ambia
|
6101
|
Preventative
Maintenance
|
No Impact to
Shippers Expected
|
None
|
|
04/26/2021
|
05/07/2021
|
Independence
|
5607
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
09/14/2021
|
10/15/2021
|
Tuscola
|
80034
|
M&R
Upgrade
|
No Impact to
Shippers Expected
|
Xenia 80034
|
|
10/11/2021
|
10/23/2021
|
Tuscola
|
100-1/-2
|
PECO Filter Replacement Phase 2
|
Capacity through Tuscola may be
limited; IT and Secondary Out of Path nominations may be limited
|
None
|
|
04/12/2021
|
04/23/2021
|
Independence
|
5606
|
Minor AI
|
No
Impact to Shippers Expected
|
None
|
|
09/27/2021
|
10/25/2021
|
Tuscola
|
100-1/-2
|
PECO Filter Replacement Phase 1
|
Capacity through Tuscola may be
limited; IT and Secondary Out of Path nominations may be limited
|
None
|
|
04/05/2021
|
04/19/2021
|
Epps
|
North
Storage Field
|
Pipe
Replacement
|
No
Impact to Shippers Expected
|
None
|
|
05/17/2021
|
05/17/2021
|
Joppa
|
MER A
|
ABV
Replacement
|
No
Impact to Shippers Expected
|
None
|
|
04/05/2021
|
04/16/2021
|
Longville
|
4522
|
Major AI
& Station ESD
|
No
Impact to Shippers Expected
|
None
|
|
07/07/2021
|
07/11/2021
|
Shaw
|
100-3
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
07/13/2021
|
07/17/2021
|
Independence
|
100-3
|
Tool Run
|
No
Impact to Shippers Expected
|
None
|
|
06/01/2021
|
06/21/2021
|
Ambia
|
100-1
|
Anomaly
Digs
|
No
Impact to Shippers Expected
|
None
|
|
05/13/2021
|
05/13/2021
|
Joppa
|
Station
|
ESD
|
No
Impact to Shippers Expected
|
None
|
|
10/13/2021
|
10/23/2021
|
Cypress
|
Kaplan 200-3
Line
|
Pipe
Replacement
|
No Impact to
Shippers Expected
|
None
|